Staff Report # 2436/06
November 23, 2006
Memorandum
To: The Chair and Members of the Board
of Directors Mississippi Valley Conservation
From: John Price, P.Eng.
Watershed Management Coordinator
Re: Shirley’s Brook Two-Zone Policy
City of Ottawa (Kanata)
Shirley’s Brook is one of two main subwatersheds within the urban
portions of the former City of Kanata (see Figure 1.1- Shirley’s
Brook/Watts Creek Subwatershed Study - Study Area). It has a total
drainage area of 2700 hectares (27 km 2 ) and outlets to the Ottawa
River at Shirley’s Bay. The total channel length, along the main
branch, is 12.4 kilometres.
The Shirley’s Brook watercourse has several branches with the
confluence of the three branches northeast of the intersection of
Klondike Road and March Road. The headwaters of Shirley’s Brook are
located within the poorly drained wetlands of the March Ridge. The main
channel commences west of Goulbourn Forced Road continuing northeast
through the Kanata North Business Park and northwest to Klondike Road.
The main watercourse then meanders east, parallel to Klondike Road, to
the DND property where it follows 4th Line Road (March Valley Road)
before turning east to empty into the Ottawa River at Shirley’ s Bay
(see Figure 3 – Comparison of Meander Belt Widths & Flood Plain
Lines on Shirley’s Brook). The headwaters of Shirley’s Brook is not
urbanized and the existing urban area is mainly located along the main
branch of Shirley’s Brook on either side of March Road.
Planning History
1) Water Management Plan for Shirley’s
Brook, Kizell Drain, Watts Creek
and Harwood Creek (1989)
In 1989 the “Water Management Plan for Shirley’s Brook, Kizell Drain,
Watts Creek and Harwood Creek – Phases I and II” was prepared by A. J.
Robinson and Associates Inc. for Mississippi Valley Conservation (MVC).
One of the products of this study was updated flood plain mapping for
Shirley’s Brook. The Regulatory (1:100 year) flood plain along
Shirley’s Brook is generally confined within the valley section of the
brook. The exception to this is the reach of the brook downstream
(east) of March Road. For this reach, due to the flat topography, (100
year flow is approximately 30 m 3 /s) the flood plain is wide , shallow
and unconfined.
Figure 3 generally shows the existing flood plain for Shirley’s Brook
in green. The culvert crossing under the railway line is perched by
approximately 0.5 metres which causes an artificially high upstream
flood plain elevation. This results in the flood plain width being
overly wide and spilling north along the ditch to the next culvert
conveying flow east under the railway line. Between the railway line
and 4 th Line Road (March Valley Road) the Regulatory flood plain is
unconfined with spill areas both north and south.
The Water Management Plan concludes that “With correct planning and
drainage design the spill zone through the Kanata North Business Park
can be eliminated and the channel and flood plain between Hwy. 17
(March Road) and Klondike Road can be modified to accommodate runoff
from future land use conditions”. The Phase II report, identified a
flood fringe area where flood
depths are less than 1.0 metres, during the 1:100 year flood, and
infilling may be allowed.
2) Kanata North Urban Expansion
Shirley’s Brook Watershed Master
Drainage Study (1992 )
In April of 1991, Cumming Cockburn Limited completed, on behalf of the
City of Kanata and the Regional Municipality of Ottawa-Carleton, a
planning study which examined the relevant planning, environmental,
servicing and transportation issues associated with expansion of the
urban boundary of Kanata to north of Klondike Road. The goal of the
study was to examine the existing municipal and regional policies
regarding growth and urban expansion, the existing physical features of
the study area and the existing and proposed servicing and
transportation infrastructure, in order to determine if and to what
extent the “Kanata North Urban Area” could be expanded.
The Kanata North Urban Expansion Shirley’s Brook Master Drainage Study,
completed subsequent to the original planning study, addressed the
drainage requirements associated with the area of the proposed urban
expansion identified in Figure 1.2 (Study Area) taken from the report.
The Master Drainage Study included a specific encroachment analysis.
The introduction
to Section 5.0 Encroachment Analysis of the Master Drainage Study
states:
In a previous study completed by the
Conservation Authority (e.g. Report entitled “Water Management Plan for
Shirley’s Brook, Kizell Drain, Watts Creek, Harwood Creek, Phase II:
Water Management Alternatives and Implementation”) it was acknowledged
that because of the shallow depths of flooding and the low velocities,
infilling within the flood fringe areas would be acceptable provided
that a number of concerns are satisfied. They include:
- No negative impacts on flood plain hydraulics;
- No negative impacts on flood hazards downstream or within the
development site;and
- No adverse impacts on any wetlands, environmentally sensitive
areas, fisheries
- habitat, etc.
The encroachment analysis is based on the development limits identified
on the preferred concept plan given in the Kanata North Urban Expansion
Study. The environmental sensitivity of the area was taken into
consideration during the preparation of the plan.
Section 7.0 Conclusions and Recommendations of the Master Drainage
Report includes several recommendations regarding the potential
encroachment into the Regulatory flood plain between March Road and 4
th Line Road (March Valley Road).
7.2 Urban Encroachment
1. All development located within the
encroachment area would be protected to the 100 year flood levels. New
development would therefore not be subjected to any increased flood
hazards. For design of basement elevations the hydraulic grade line
would be based on the 100 year computed flood level within the
designated stormwater management facility.
2. Encroachment based on the limits as
identified on the recommended concept plan for the Kanata North Urban
Expansion Area would result in a small loss of natural channel storage
under the 100 year design storm event. This could be accommodated by
either upgrading Shirley’s Brook to offset any negative impacts or by
introducing flow control structure. Construction of two
non-operational flow control structures would offset the impact of
encroachment on lost storage along Shirley’s Brook.
Alternatively, the Shirley’s Brook drainage system could be upgraded to
offset any negative impacts associated with the loss of available
natural storage. This approach would require possible improvements to
the CNR and 4 th Line Road culverts.
3. If properly designed the proposed
infilling activity to accommodate the proposed development would have
no significant impact on the hydrologic, hydraulic and environmental
conditions of the study area.
3) Kanata North Expansion Area Phase
One Report (1998)
In 1990, a group of landowners in what became the Kanata North Urban
Expansion Area (KNUEA) applied to the City of Kanata and the Regional
Municipality of Ottawa-Carleton to amend their Official Plans. In
response to this, the City of Kanata retained Cumming Cockburn to
prepare a concept plan that dealt with land use, development,
infrastructure, transportation and
environmental issues. This study was the basis for Regional Official
Plan Amendment 41 (ROPA 41) that was adopted by Regional Council in
March 1994. The Ministry of Municipal Affairs refused to approve ROPA
41 and it was referred to the Ontario Municipal Board (OMB).
Following the hearing in July 1995, the OMB approved ROPA 41 in January
1996.
The amendment provided a new designation called West Urban Centre
Expansion Area and it provided for an expansion of approximately 202
hectares (500 acres) as shown in Figure 1. The OMB approval of ROPA 41
was based on studies being completed as listed in Section 2.4.1,
Policy 8 of the Regional Official Plan as follows:
8. Re-designate the Kanata North
Expansion Area shown on Schedule B to
allow urban development to proceed, subject to studies to address the
matters outlined below to the satisfaction of Council. In the event
that the studies are not completed to the satisfaction of Council, the
lands shall be re-designated to General Rural. The studies shall
address the:
- provisions of transportation and other infrastructure which
fulfils
Regional and local functions;
- mix and variety of housing types;
- variety of employment opportunities;
- Environmental Impact Study for lands within 120 metres of the
South
March Highlands/Wetlands to be completed to
the satisfaction of the
Ministry of Natural Resources;
- phasing of development related to both the provision and the cost
of
providing transporation and other infrastructure;
- policy approaches which Council might wish to consider as to
financial arrangements and requirements for any
needed infrastructure
improvements associated with the Kanata North Expansion Area;
- present and future roles and needs of the South March Community
and
the impact of development on any of the Kanata North
Expansion Area
lands on the south March Community. Reassessment of the planned
function of various components of the South March Community may be
necessary;
- ability of the Kanata North Expansion Area to satisfy the
Provincial
Policy Statement .
The Kanata North Expansion Area Phase One Report addressed future
stormwater systems in Section 2.8.3 of the report. The report
references the analysis completed in both the 1989 A. J. Robinson
Report and the 1992 CCL report and recommended the adoption of the
floodway/flood fringe approach within the study area. There was also a
recommendation that Shirley’s Brook should have a 15 metre setback on
either side to protect fish habitat identified in the study.
4) Shirley’s Brook Watts Creek Sub
watershed Study (1999)
The City of Kanata and the Region of Ottawa-Carleton prepared a
subwatershed study plan for Shirley’s Brook and Watts Creek
subwatersheds to ensure that planning future development proceeds in an
environmentally sound manner. The plan makes recommendations as to how
water resources and related subwatershed features and ecological
functions should be protected
and enhanced to coincide with existing and changing land use. The
subwatershed study identified several structures, in the three
subwatersheds, with inadequate conveyance capacity thus having a direct
impact on flood susceptibility as the resulting upstream levels
upstream of the structure result in an increase to the extent of the
land area flooded. Consequently, the report continues,
hydraulic structure improvements including enlargement and/or
replacement of existing bridges and roadway culverts should be
considered as part of any structural upgrading works initiated by the
municipality. The Shirley’s Brook crossing under the railway line is
listed as one such structure.
The subwatershed recognizes that
development and site alterations
proposed in hazardous lands associated with flooding must demonstrate
that all of the following can be achieved:
- the hazard can be safely addressed
and the development and site alteration is carried out in accordance
with established standards and procedures;
- new hazards are not created and existing hazards are not
aggravated;
- no adverse environmental impacts will result;
- vehicles and people have a way of safely entering and exiting the
area during times of flooding, erosion and other emergencies; and
- the development does not include institutional use essential
emergency services or the disposal, manufacture, treatment or storage
of hazardous substances.
5) Kanata North Environmental/Stormwater Management Plan (2001)
The Shirley’s Brook Watts Creek Subwatershed Study recommended
an
integrated land and water management approach to development of areas
in the North Kanata in the Shirley’s Brook subwatershed. The
Subwatershed Study made specific recommendations pertaining to natural
area preservation and enhancement and target water quality objectives
to guide future
development. Additional detail in the form of an
Environmental/Stormwater Management Plan was required to provide a
“bridge” between the guidance of the Subwatershed Study and the need
for specific stormwater strategies and natural environmental protection
measures for the development areas in Kanata North.
The study area for the plan included lands in the Kanata North Urban
Expansion Area centred around March Road and Klondike Roads, although
existing and ongoing development areas in the Kanata North Business
Area immediately to the south were also investigated for opportunities
for additional stormwater control or natural environmental enhancement
(Figure 1
Kanata North Study Area). Specifically for the Kanata North Urban
Expansion Area lands between March Road and 4 th Line Road (March
Valley Road) the plan addressed four main issues
- location and conceptual sizing of stormwater management facilities
- flood plain management options
- functional design of stream restoration plans
- natural area protection
Figure 11 ( Kanata North Urban Expansion Area Recommended Facility
Locations East of Shirley’s Brook) shows the recommended stormwater
management facility locations with two centralized off-line facilities
north and south of Shirley’s Brook at 4 th Line Road (March Valley
Road). The following flood plain
management recommendations were made:
1. The City of Ottawa as
the
planning authority should recommend to the MVCA that it wishes to
pursue two-zone approach to flood plain management for Shirley’s Brook
from 4 th Line Road to the confluence of the north and south branch.
2. In pursuing the two-zone
option, then as part of the overall site design land developers should
undertake hydrotechnical analyses to determine an optimized strategy
for alteration of the flood plain of Shirley’s Brook. The analysis
should:
- be based on meeting targets with respect to downstream 100 year
flood flows, 100 year flood levels and flood plain storage capacity;
- demonstrate through hydraulic analysis that a proposed flood
plain alteration design will not increase the peak 100 year flow on the
downstream side of 4 thLine Road, will not increase the peak 100 year
flood level at the upstream end of the study area of concern and will
not reduce flood plain storage within the subject lands.
- demonstrate how proposed SWM ponds can be integrated within a
proposed flood plain alteration design while meeting the site runoff
control targets;
- be carried out in consultation with MVCA staff who can provide
guidance on acceptable flood plain alteration plans and acceptability
of marginal changes in flood levels or flood plain storage capacities
in critical areas.
Present Development Plans
Subsequent to the completion and approval of the Kanata North
Environmental/Stormwater Management Plan, plans for development of the
Kanata North Urban Expansion lands have progressed. Figure 2 (Klondike
Road Lands - Land Use Plan) shows the proposed land use in the area. A
subdivision, indicated in Figure 2 by lotting fabric, has received
draft plan approval.
In support of this draft plan of subdivision application, several
studies and analyses have been completed to implement and refine the
concepts and recommendations presented in the Kanata North
Environmental/Stormwater Management Plan.
These analyses include:
- flows calculated using an updated hydrologic model of the
Shirley’s Brook subwatershed upstream of 4 th Line Road assembled by
consolidating separate hydrologic models created for various
development areas into an overall model of the subwatershed;
- water levels and flow velocities calculated using a hydraulic
(backwater) model updated based on field surveys and updated
topographic mapping within the development area.
These updated models were also modified to assess post-development
conditions with respect to changes in land use, proposed filling in the
flood fringe areas and proposed new crossings of Shirley’s Brook. The
proposed design includes two stormwater management ponds at 4 th Line
Road to provide post-development water quality control and erosion
control storage for the
subject area. Two dry ponds, located upstream of 4 th Line Road, will
replace flood plain storage lost by filling in the flood fringe areas
Downstream of 4 th Line Road (March Valley Road) is the DND property
(Connaught Rifle Range). There are further existing spill areas through
this property, but no buildings are flooded (open fields) and no future
development is expected.
Discussion
As detailed above, there is substantial history through various
reports, supporting the application of the two zone concept for flood
plain management for the Shirley’s Brook flood plain between 4 th Line
Road (March Valley Road) and March Road when the Kanata North Urban
Expansion Area developed.
The two-zone concept recognizes the fact that the flood plain can often
be divided into two zones: the floodway, where the majority of the flow
is conveyed and the flood fringes which exist on both sides of the
floodway.
Section 3.1 of the Provincial Policy Statement (PPS) supports the
selective application of the two-zone concept for flood plain
management where development and site alteration may be permitted in
the flood fringe subject to appropriate floodproofing. Section 3.1.6
of the PPS states in part:
Development and site alterations may be
permitted in those portions of hazardous lands where the effects and
risk to public safety are minor so as to be managed or mitigated in
accordance with provincial standards, as determined by the
demonstration and achievement of all of the following:
a) development and site alteration is
carried out in accordance with flood proofing standards, protection
works standards and access standards;
b) vehicles and people have a way of safely entering and exiting the
area during times of flooding, erosion and other emergencies;
c) new hazards are not created and existing hazards are not aggravated;
and
d) no adverse environmental impacts will results.
The analysis that has been completed, demonstrates that these “tests”
can be met in the development of this area.
The “Technical Guide – River and Stream Systems: Flood Hazard Limit”
states that the extent of the floodway is to be determined based on
local watershed conditions, such as critical flood depths and velocity,
existing and proposed development and potential for upstream and
downstream impacts. Generally, flow depths in excess of 1 metre and/or
flow velocities above 1
m/ s can create significant hazards for developments. The average flood
depth, during the 1:100 year flood, in the proposed flood fringe areas
is approximately 0.4 metres and the average flow velocity is between
0.15m/ s and 0.3 m/ s.
There are reaches of Shirley’s Brook, (e.g. between 4 th Line Road and
the railway line) where the 1:100 year flood plain is unconfined and
spills uncontrolled both the north and south. Filling in the flood
fringe will result in a confined and defined flood plain limit. The
area upstream of the railway line, as described earlier, experiences
artificially high flood levels and an overly wide
flood plain width. Again Section 4.2 of the “T echnical Guide – River
and Stream Systems: Flood Hazard Limit” addresses this situation when
it states, in part:
It is recommended that the upstream
flood line should make allowances
for the backwater effects caused by a structure. Where this assumption
results in unacceptable conditions the culvert should be replaced or
alternatively, where feasible, the two-zone concept should be
introduced.
Although the replacement or enlargement of the culvert crossing is not
feasible at this time, a scenario was reviewed where the crossing was
removed from the hydraulic model. The result of this scenario was a
substantial reduction in the width of the 1:100 year flood plain
essentially to within the proposed corridor around Shirley’s Brook to
be left after development. The change in riparian flood plain storage,
for this scenario, will be addressed by completing additional grading
within the corridor.
The proposed design of development along this reach of Shirley’s Brook
will include:
- The filling of all flood fringe lands to a minimum of 0.3 metres
above the 1:100 year flood level before development occurs
- Minimal change (maximum 4%) in flows and no change in timing of
hydrographs at 4 th Line Road. No increase in water levels or flow
velocities downstream of 4 th Line Road. No increase in flood levels at
the upstream end of the site.
- The elimination of spill areas of the flood plain along this
reach. There will still be one spill area to the north along 4 th Line
Road that can only be addressed when the road is upgraded.
- The underside of footings for all structures will be a minimum of
0.3 metres above the hydraulic gradeline elevation in the storm sewers.
Since the storm sewers discharge to the
stormwater management pond at 4 th Line Road The starting 1:100 year
water level is approximately 2 metres lower at this location, than
upstream of the railway line. This results in basement elevations for
dwellings upstream (east) of the railway line that are approxi mately
1.5 metres below the 1:100 year flood plain elevation at that location,
however there is no direct connection of storm sewers to the brook at
that location. The minimum ground elevation at the lot boundary will be
0.3 metres above the 1:100 year flood level and the at the proposed
dwelling location, which is approximately 10 metres from the property
line, the ground elevation is approximately 0.5 metres higher than the
1:100 year flood level. The peak water level occurs for approximately 4
hours. This relatively short duration time frame will not cause
groundwater levels to rise high enough at the dwellings to impact the
basements.
- No reduction in riparian storage upstream of the railway line and
a 50-100% increase in total flood plain storage downstream of the
railway line provided by the flood plain dry ponds. Approximately 70%
of all the existing flood plain storage for this entire reach of
Shirley’s Brook is being replicated in the dry ponds.
Recommendation:
The Board of Directors approve the application of the two-zone
floodway/flood fringe concept for the administration of the Regulatory
flood plain of Shirley’s Brook between the confluence of the north and
south branch downstream to March Valley Road.
Map references on
page 17